SIMSBURY AIRPORT FEASIBILITY STUDY
Study Meeting #2 Agenda
April 15, 2008, 2:00 p.m.
Town of Simsbury
A. Introductions
* Town Personnel/Officials
* Advisory Committee
B. Project Status (Study Tasks)
1. Airport Inspection & Environmental Review (completed)
Findings discussed at Study Meeting #1 and in Working Paper #1
2. Airport Development Evaluation (ongoing – Chapter 2)
Activity Forecasts
1. Status Quo Scenario
2. Growth Scenario
Development Plan Issues
1. Satisfy FAA Design Standards
2. Runway Extension
3. Property Acquisition
4. Landside Development
Potential Recommendations
3. Airport Capital Improvement Plan (ongoing – Chapter 2)
Status Quo Scenario
Growth Scenario
4. Financial Feasibility Analysis (ongoing – Chapter 3)
5. Economic Impact Analysis (completed – Chapter 3)
6. Management/Ownership Options
7. Recommendation & Implementation Plan
8. Public Outreach & Coordination (ongoing)
Scoping Meeting - October 16, 2007
Kickoff Meeting – November 15, 2007
Study Meeting #1 – January 16, 2008
Public Information Meeting - January 16, 2008
Study Meeting #2 – April 15, 2008
Study Meeting #3 – June*
Final Public Information Meeting – June*
*Need to set date to discuss Full Draft Report
C. Discussion
|